The stretch of the Via Baltica motorway through Poland’s Rospuda valley, which has become a test case for EU environmental safeguards, has once again hit a roadblock.
[mailchimp_signup][/mailchimp_signup]The regional administrative court in Warsaw has cancelled the environmental consent for the 17-kilometre Augustow bypass. It is the third legal judgement against the scheme, after decisions in April and December saying the road’s environmental impact assessment was inadequate under EU law.
The bypass is due to go through the Augustow forest and Rospuda wetlands, which are under protection as Natura 2000 sites. Anyone proposing a road scheme through such a protected area is obliged by the EU habitats directive to explore alternative routes. Polish environmental NGOs have regularly pointed out that an alternative does exist but it has not been considered by the Polish authorities.
Magda Stoczkiewicz of CEE Bankwatch Network said: ‘The Polish authorities must start reconsidering possible alternative routes for the bypass.’
Cutting regulation is a gift to China’s car makers
Europe’s carmakers have a unique competitive advantage over their Chinese counterparts - yet the Omnibus proposals risk throwing it away
How to help Indonesia clean up its minerals act
Indonesia is big when it comes to the new race to secure minerals and cleantech. But as nickel demand takes off, so does its environmental and social...
Europe needs a cleantech State Aid overhaul
The EU wants to lead the cleantech transition - for that it needs to replace its traditional project-by-project State Aid system with automatic, banka...